Solar project CLPT G14, Laramie County

Solar project CLPT G14, Laramie County is a 150 MW solar request built and operating in the West interconnection queue, in Laramie County, Wyoming, connecting to Black Hills Cheyenne Light Fuel and Power Transmission.

Queue statusOperating
  1. PlanningQueued May 2021 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
CLPT G14
Grid region
West (non-ISO utilities)
Utility / transmission owner
Black Hills Cheyenne Light Fuel and Power Transmission
Developer
South Cheyenne Solar, LLC
Connection point (POI)
Sweetgrass 115kV Substation
Location
Laramie County, Wyoming
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
In-Service
Queue status
Operational
Entered queue
24 May 2021
Proposed online date
December 2023

Location

Marker shows the centre of Laramie County; the queue data does not give exact sites.

Power plants in Wyoming · Transmission lines in Wyoming

Other requests in Laramie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem