Anemoi Energy Storage

Anemoi Energy Storage is a 205 MW other request built and operating in the ERCOT interconnection queue, in Hidalgo County, Texas.

Queue statusOperating
  1. PlanningQueued Sep 2021 (completed)
  2. ConsentedJan 2022 (completed)
  3. Construction (completed)
  4. OperatingJun 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0369
Grid region
ERCOT (Texas)
Developer
Anemoi Energy Storage, LLC
Connection point (POI)
8574 POMELO 345kV
Location
Hidalgo County, Texas
Technology
Other: 205 MW
Total requested
205 MW
Study phase
IA
Queue status
Operational
Entered queue
2 September 2021
Agreement signed
5 January 2022
Proposed online date
June 2024
Came online
June 2024

Location

Marker shows the centre of Hidalgo County; the queue data does not give exact sites.