ONSHORE WIND Β· ERCOTHart Wind
Hart Wind is a 163 MW onshore wind request built and operating in the ERCOT interconnection queue, in Castro County, Texas.
Request details
- Queue ID
- 24INR0116
- Grid region
- ERCOT (Texas)
- Developer
- Hart Wind Project LLC
- Connection point (POI)
- Tap 345kV 23912 OGALLALA - 23920 BLACKWATER DRAW SWITCH
- Location
- Castro County, Texas
- Technology
- Wind: 163 MW
- Total requested
- 163 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 20 October 2021
- Agreement signed
- 6 October 2023
- Proposed online date
- November 2025
- Came online
- November 2025
Location
Marker shows the centre of Castro County; the queue data does not give exact sites.
Other requests in Castro County
- Acker BESSBattery storage Β· 301 MW Β· agreement signed
- Castro SolarSolar Β· 225 MW Β· agreement signed
- Nazareth SolarSolar Β· 203 MW Β· agreement signed
- Onshore wind project GEN-2018-089, Castro CountyOnshore wind Β· 196 MW Β· agreement signed
- Onshore wind project GEN-2017-146, Castro CountyOnshore wind Β· 152 MW Β· agreement signed
- Cavell WindOnshore wind Β· 641 MW Β· in study
- Cavell SolarSolar Β· 502 MW Β· in study
- Solar project GEN-2024-099, Castro CountySolar Β· 300 MW Β· in study
- Solar + storage project GEN-2024-050, Castro CountySolar + storage Β· 300 MW Β· in study
- Ogalalla StorageBattery storage Β· 252 MW Β· in study
- Scarlet SolarSolar Β· 180 MW Β· in study
- Shifting Gale WindOnshore wind Β· 289 MW Β· suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem