United States › Grid › Interconnection queues › New Mexico
SOLAR · WESTSolar project GI-TC-2021-05, Mckinley County
Solar project GI-TC-2021-05, Mckinley County is a 200 MW solar request built and operating in the West interconnection queue, in Mckinley County, New Mexico, connecting to Tri-State Generation and Transmission Association.
Request details
- Queue ID
- GI-TC-2021-05
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Tri-State Generation and Transmission Association
- Connection point (POI)
- PEGS 230kV Station
- Location
- Mckinley County, New Mexico
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 15 March 2021
- Agreement signed
- 1 November 2023
- Proposed online date
- November 2023
- Came online
- November 2023
Location
Marker shows the centre of Mckinley County; the queue data does not give exact sites.
Power plants in New Mexico · Transmission lines in New Mexico
Other requests in Mckinley County
- Other project IA-PNM-2023-10, Mckinley CountyOther · 210 MW · in study
- Battery storage project GI-SISS-2025-03, Mckinley CountyBattery storage · 200 MW · in study
- Solar + storage project IA-PNM-2023-06, Mckinley CountySolar + storage · 199 MW · in study
- Onshore wind project IA-PNM-2025-15, Mckinley CountyOnshore wind · 190 MW · in study
- Solar + storage project IA-PNM-2020-06, Mckinley CountySolar + storage · 90.0 MW · in study
- Solar + storage project IA-PNM-2018-02, Mckinley CountySolar + storage · 150 MW · suspended
- Solar + storage project IA-PNM-2019-08, Mckinley CountySolar + storage · 125 MW · suspended
- Ambrosia SolarSolar + storage · 90.0 MW · suspended
- Wildcat Solar Power PlantSolar + storage · 90.0 MW · suspended
- Arroyo SolarSolar + storage · 300 MW · built
- Red Mesa WindOnshore wind · 102 MW · built
- Solar + storage project IA-PNM-2022-09, Mckinley CountySolar + storage · 375 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem