Wildcat Solar Power Plant

Wildcat Solar Power Plant is a 90.0 MW solar + storage request suspended in the West interconnection queue, in Mckinley County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusPaused / redesign
  1. PlanningQueued Oct 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
IA-PNM-2020-12
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
YN line 115 kV
Location
Mckinley County, New Mexico
Technology
Solar: 90.0 MW · Battery
Total requested
90.0 MW
Service type
Energy only (ERIS)
Study phase
LGIA executed 9/3/24. In 3-yr Suspension effective 9/12/24
Queue status
Suspended
Entered queue
14 October 2020
Proposed online date
May 2023

Location

Marker shows the centre of Mckinley County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Mckinley County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem