United States › Grid › Interconnection queues › Virginia

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in Virginia

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown21523.0 GW
Active in queue30.3 GW287 requests
Agreement signed7,318 MW72 requests
Withdrawn86886.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

215 requests · page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Cvow 2, Oss 2 – T2G07
Offshore wind · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
836 MWIn study City Of Chesapeake, VAPJM Sep 2019target 2032
Cvow 1, Oss 1 - T1L11
Offshore wind · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
833 MWIn study City Of Chesapeake, VAPJM Sep 2019target 2032
Cvow 3, Oss 3 – T3G15
Offshore wind · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
820 MWIn study City Of Chesapeake, VAPJM Sep 2019target 2032
Gas project AH1-712, Fluvanna County
Gas · Tenaska Power Generation, LLC
776 MWIn study Fluvanna, VAPJM Apr 2025
Gas project AH1-723, Fluvanna County
Gas · Tenaska Power Generation, LLC
776 MWIn study Fluvanna, VAPJM Apr 2025
Battery storage project AH1-716, James City County
Battery storage · Cardinal Energy Storage East, LLC
650 MWIn study James City, VAPJM Apr 2025
Chesterfield CT Units 1 and 2
Gas · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
569 MWIn study Chesterfield, VAPJM Sep 2019target 2029
Battery storage project AH1-727, Loudoun County
Battery storage · Cardinal Energy Storage East, LLC
425 MWIn study Loudoun, VAPJM Apr 2025
Solar project AG2-570, Brunswick County
Solar · Zeus Energy, LLC
400 MWIn study Brunswick, VAPJM Mar 2025target 2024
Solar project AG2-436, Sussex County
Solar · Monarch Solar, LLC
350 MWIn study Sussex, VAPJM Apr 2025target 2023
Honeybee Solar, LLC
Solar · Honeybee Solar Energy, LLC
301 MWIn study Brunswick, VAPJM Jan 2025target 2025
Battery storage project AH2-133, City Of Chesapeake County
Battery storage
300 MWIn study City Of Chesapeake, VAPJM Mar 2022target 2027
Solar project AI1-203, Lunenburg County
Solar
300 MWIn study Lunenburg, VAPJM Sep 2022target 2027
Battery storage project AI1-017, Surry County
Battery storage
300 MWIn study Surry, VAPJM Apr 2022target 2026
Battery storage project AI1-018, Spotsylvania County
Battery storage
300 MWIn study Spotsylvania, VAPJM Apr 2022target 2026
Solar project AH2-322, Pittsylvania County
Solar
290 MWIn study Pittsylvania, VAPJM Mar 2022target 2025
Solar project AH2-069, Wythe County
Solar
250 MWIn study Wythe, VAPJM Jan 2022target 2025
Battery storage project AG2-360, Smyth County
Battery storage · Laurel Creek Energy Storage LLC
250 MWIn study Smyth, VAPJM Feb 2025target 2024
Battery storage project AI1-185, Augusta County
Battery storage
210 MWIn study Augusta, VAPJM Sep 2022target 2027
Axton Solar
Solar
201 MWPaused / redesign Henry, VAPJM Mar 2019target 2025
Solar project AG2-182, Frederick County
Solar · ACE Development Company, LLC
200 MWIn study Frederick, VAPJM Feb 2025target 2022
Battery storage project AH2-102, Franklin County
Battery storage
200 MWIn study Franklin, VAPJM Jan 2022target 2026
Battery storage project AH1-263, Spotsylvania County
Battery storage · Scarlet Energy Storage LLC
200 MWIn study Spotsylvania, VAPJM Feb 2025target 2025
Battery storage project AI1-013, Charles City County
Battery storage
200 MWIn study Charles City, VAPJM Apr 2022target 2026
Solar project AG2-077, Charlotte County
Solar · Virginia Electric and Power Company
200 MWIn study Charlotte, VAPJM Jan 2025target 2024
Courthouse Solar
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
167 MWIn study Charlotte, VAPJM Mar 2020target 2031
Battery storage project AI2-045, City Of Virginia Beach County
Battery storage
150 MWIn study City Of Virginia Beach, VAPJM Feb 2023target 2023
Battery storage project AI2-456, King George County
Battery storage
150 MWIn study King George, VAPJM Mar 2023target 2027
Battery storage project AI2-001, Caroline County
Battery storage
150 MWIn study Caroline, VAPJM Oct 2022target 2028
Solar project AH2-350, Cumberland County
Solar
150 MWIn study Cumberland, VAPJM Mar 2022target 2025
Solar project AG2-069, Brunswick County
Solar · Virginia Electric and Power Company
150 MWIn study Brunswick, VAPJM Feb 2025target 2025
Battery storage project AG2-288, Frederick County
Battery storage · Rockline Reliability Center LLC
150 MWIn study Frederick, VAPJM Feb 2025target 2023
Battery storage project AI2-002, Washington County
Battery storage
150 MWIn study Washington, VAPJM Oct 2022target 2028
Battery storage project AH2-144, King George County
Battery storage
150 MWIn study King George, VAPJM Feb 2022target 2027
Wild Indigo Solar
Solar
150 MWPaused / redesign Surry, VAPJM Oct 2017target 2026
Solar project AI2-038, Spotsylvania County
Solar
150 MWIn study Spotsylvania, VAPJM Jan 2023target 2027
Solar project AG2-581, Brunswick County
Solar · Bellflower Holdings, LLC
150 MWIn study Brunswick, VAPJM Jan 2025target 2024
Battery storage project AI2-044, City Of Virginia Beach County
Battery storage
150 MWIn study City Of Virginia Beach, VAPJM Feb 2023target 2023
Battery storage project AH2-291, Brunswick County
Battery storage
150 MWIn study Brunswick, VAPJM Mar 2022target 2026
Battery storage project AG2-088, Chesterfield County
Battery storage · Hermon Energy Center, LLC
150 MWIn study Chesterfield, VAPJM Feb 2025target 2022
Battery storage project AG2-270, Halifax County
Battery storage · Clover Storage, LLC
150 MWIn study Halifax, VAPJM Apr 2025target 2025
Maroon Solar
Solar
149 MWPaused / redesign Culpeper, VAPJM Sep 2018target 2027
Enclave Solar Energy Center
Solar
149 MWPaused / redesign Sussex, VAPJM Jan 2019target 2027
Solar project AI2-037, King And Queen County
Solar
142 MWIn study King And Queen, VAPJM Jan 2023target 2027
Solar project AH2-349, Halifax County
Solar
142 MWIn study Halifax, VAPJM Mar 2022target 2025
Solar project AG2-442, Charlotte County
Solar · Taro Solar LLC
140 MWIn study Charlotte, VAPJM Apr 2025target 2024
Battery storage project AI1-186, Shenandoah County
Battery storage
140 MWIn study Shenandoah, VAPJM Sep 2022target 2027
Battery storage project AH2-083, Caroline County
Battery storage
140 MWIn study Caroline, VAPJM Jan 2022target 2027
Solar project AG2-152, Pittsylvania County
Solar · Virginia Electric and Power Company
131 MWIn study Pittsylvania, VAPJM Mar 2025target 2024
Battery storage project AI1-183, Richmond County
Battery storage
130 MWIn study Richmond, VAPJM Sep 2022target 2027
Page 1 of 5

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20172025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)