United States โบ Grid โบ Interconnection queues โบ Rhode Island
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in Rhode Island
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Offshore Wind Offshore wind |
1,200 MW | Withdrawn / abandoned |
| Clear River Gas |
1,030 MW | Withdrawn / abandoned |
| Combined Cycle Gas |
870 MW | Withdrawn / abandoned |
| Wind Onshore wind |
536 MW | Withdrawn / abandoned |
| Exciter Upgrades Gas |
492 MW | Withdrawn / abandoned |
| Wind Onshore wind |
450 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
415 MW | Withdrawn / abandoned |
| Wind Onshore wind |
385 MW | Withdrawn / abandoned |
| Offshore Wind Offshore wind |
352 MW | Withdrawn / abandoned |
| Combined Cycle( see # 201) Gas |
320 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
313 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
305 MW | Withdrawn / abandoned |
| Combined Cycle Gas |
285 MW | Withdrawn / abandoned |
| Combustion Turbine Generator Gas |
238 MW | Withdrawn / abandoned |
| Combustion Turbine (Alt to Q523) Gas |
234 MW | Withdrawn / abandoned |
| Combustion Turbine Gas |
227 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
200 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
180 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
170 MW | Withdrawn / abandoned |
| Offshore Wind Increase (Q781) Offshore wind |
167 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
166 MW | Withdrawn / abandoned |
| Converts QP 164 to combined cycle facility and inc Gas |
162 MW | Withdrawn / abandoned |
| Internal Combustion Gas |
119 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
109 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
108 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
108 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
102 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
62.8 MW | Withdrawn / abandoned |
| Solar (QF) Solar |
56.5 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
55.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
50.4 MW | Withdrawn / abandoned |
| Kent County - NG WRI DG Area Study #2 >5 MW Solar |
49.8 MW | Withdrawn / abandoned |
| Wood River Substation - Western RI DER Study #3 Solar |
49.0 MW | Withdrawn / abandoned |
| Solar (QF) Solar |
40.0 MW | Withdrawn / abandoned |
| Combined Cycle Upgrade Gas |
40.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
40.0 MW | Withdrawn / abandoned |
| Wood River - NG WRI DG Area Study #2 >5 MW Solar |
34.4 MW | Withdrawn / abandoned |
| Solar Solar |
30.0 MW | Withdrawn / abandoned |
| Wind Onshore wind |
28.8 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
27.4 MW | Withdrawn / abandoned |
| Combined Cycle Gas |
27.0 MW | Withdrawn / abandoned |
| Land Fill Gas Other |
25.0 MW | Withdrawn / abandoned |
| Kent County Substation - Western RI DER Study #3 Solar |
21.7 MW | Withdrawn / abandoned |
| Combined Cycle Uprate Gas |
21.1 MW | Withdrawn / abandoned |
| Wind Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Kent County - NG WRI DG Area Study #2 <5 MW Solar |
13.5 MW | Withdrawn / abandoned |
| Solar Solar |
11.0 MW | Withdrawn / abandoned |
| Kent County Substation - NG Western RI DG Area Study Solar |
10.4 MW | Withdrawn / abandoned |
| Solar (QF) Solar |
10.0 MW | Withdrawn / abandoned |
| Solar Solar |
10.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)