United States › Grid › Interconnection queues › Rhode Island

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 109 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Providence County, Rhode Island.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2023 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1418
Grid region
ISO-NE (New England)
Connection point (POI)
115KV Line Q143S-2 between Woonsocket and Franklin Square substations, approximately 10 miles from Woonsocket substation.
Location
Providence County, Rhode Island
Technology
Battery: 109 MW
Total requested
109 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
27 June 2023
Proposed online date
April 2027
Withdrawn
November 2023

Location

Marker shows the centre of Providence County; the queue data does not give exact sites.

Power plants in Rhode Island · Transmission lines in Rhode Island

Other requests in Providence County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem