Battery Storage

Battery Storage is a 55.0 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Providence County, Rhode Island.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2022 (completed)
  2. Withdrawn / abandonedOct 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1324
Grid region
ISO-NE (New England)
Connection point (POI)
115 kV Line T-172N approximately 1.38 mi from Farnum Pike and 1.09 mi from Putnam Pike Substations
Location
Providence County, Rhode Island
Technology
Battery: 55.0 MW
Total requested
55.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
18 October 2022
Proposed online date
December 2027
Withdrawn
October 2024

Location

Marker shows the centre of Providence County; the queue data does not give exact sites.

Power plants in Rhode Island · Transmission lines in Rhode Island

Other requests in Providence County