πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Rhode Island

GAS Β· ISO-NE

Combined Cycle

Combined Cycle is a 870 MW gas request withdrawn in the ISO-NE interconnection queue, in Newport County, Rhode Island.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2015 (completed)
  2. Withdrawn / abandonedJul 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
549
Grid region
ISO-NE (New England)
Connection point (POI)
interconnection on NGRID 115kV M13 & L14 lines connecting to Somerset and Bell Rock substations
Location
Newport County, Rhode Island
Technology
Gas: 870 MW Β· Oil
Total requested
870 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
28 May 2015
Proposed online date
May 2020
Withdrawn
July 2015

Location

Marker shows the centre of Newport County; the queue data does not give exact sites.

Power plants in Rhode Island Β· Transmission lines in Rhode Island

Other requests in Newport County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem