🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Rhode Island

GAS · ISO-NE

Tiverton Power LLC Upgrade

Tiverton Power LLC Upgrade is a 21.5 MW gas request built and operating in the ISO-NE interconnection queue, in Newport County, Rhode Island.

Queue statusOperating
  1. PlanningQueued Feb 2015 (completed)
  2. ConsentedAug 2017 (completed)
  3. Construction (completed)
  4. OperatingTarget Nov 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
525
Grid region
ISO-NE (New England)
Connection point (POI)
near Bell Rock and Somerset on NGRID 115kV lines L14 and M13.
Location
Newport County, Rhode Island
Technology
Gas: 21.5 MW
Total requested
21.5 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
25 February 2015
Agreement signed
30 August 2017
Proposed online date
November 2016

Location

Marker shows the centre of Newport County; the queue data does not give exact sites.

Power plants in Rhode Island · Transmission lines in Rhode Island

Other requests in Newport County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem