United States βΊ Grid βΊ Interconnection queues βΊ Rhode Island
GAS Β· ISO-NECHP
CHP is a 6.3 MW gas request withdrawn in the ISO-NE interconnection queue, in Newport County, Rhode Island, connecting to NGRID.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2018 (completed)
- Withdrawn / abandonedJun 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 789
- Grid region
- ISO-NE (New England)
- Utility / transmission owner
- NGRID
- Connection point (POI)
- GRID 13.8 kV supplied by 69/13.8 KV Navy Substion in RI
- Location
- Newport County, Rhode Island
- Technology
- Gas: 6.3 MW
- Total requested
- 6.3 MW
- Queue status
- Withdrawn
- Entered queue
- 28 September 2018
- Proposed online date
- June 2021
- Withdrawn
- June 2025
Location
Marker shows the centre of Newport County; the queue data does not give exact sites.
Power plants in Rhode Island Β· Transmission lines in Rhode Island
Other requests in Newport County
- Tiverton UprateGas Β· 306 MW Β· built
- Tiverton Power LLC UpgradeGas Β· 21.5 MW Β· built
- Brayton Road SolarSolar Β· 8.4 MW Β· built
- Brayton Road SolarSolar Β· 3.4 MW Β· built
- Combined CycleGas Β· 870 MW Β· withdrawn
- Combined CycleGas Β· 285 MW Β· withdrawn
- Internal CombustionGas Β· 119 MW Β· withdrawn
- SolarSolar Β· 11.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem