Brayton Road Solar

Brayton Road Solar is a 8.4 MW solar request built and operating in the ISO-NE interconnection queue, in Newport County, Rhode Island, connecting to NGRID.

Queue statusOperating
  1. PlanningQueued Dec 2019 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Sep 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
942
Grid region
ISO-NE (New England)
Utility / transmission owner
NGRID
Connection point (POI)
GRID 33F4 Feeder Connecting to Tiverton No. 2 substation
Location
Newport County, Rhode Island
Technology
Solar: 8.4 MW
Total requested
8.4 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
10 December 2019
Proposed online date
September 2024

Location

Marker shows the centre of Newport County; the queue data does not give exact sites.