United States › Grid › Interconnection queues › Rhode Island
SOLAR · ISO-NEBrayton Road Solar
Brayton Road Solar is a 3.4 MW solar request built and operating in the ISO-NE interconnection queue, in Newport County, Rhode Island, connecting to NGRID.
Request details
- Queue ID
- 941
- Grid region
- ISO-NE (New England)
- Utility / transmission owner
- NGRID
- Connection point (POI)
- GRID 33F4 Feeder Connecting to Tiverton No. 2 substation
- Location
- Newport County, Rhode Island
- Technology
- Solar: 3.4 MW
- Total requested
- 3.4 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 10 December 2019
- Proposed online date
- January 2024
Location
Marker shows the centre of Newport County; the queue data does not give exact sites.
Power plants in Rhode Island · Transmission lines in Rhode Island
Other requests in Newport County
- Tiverton UprateGas · 306 MW · built
- Tiverton Power LLC UpgradeGas · 21.5 MW · built
- Brayton Road SolarSolar · 8.4 MW · built
- Combined CycleGas · 870 MW · withdrawn
- Combined CycleGas · 285 MW · withdrawn
- Internal CombustionGas · 119 MW · withdrawn
- SolarSolar · 11.0 MW · withdrawn
- CHPGas · 6.3 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem