United States โบ Grid โบ Interconnection queues โบ Ohio
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in Ohio
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Coal project R68, Jefferson County Coal |
1,940 MW | Withdrawn / abandoned |
| Coal project I07, Jefferson County Coal |
1,860 MW | Withdrawn / abandoned |
| Gas project AH1-690, Lucas County Gas ยท CPV Oregon, LLC |
1,475 MW | Withdrawn / abandoned |
| Coal project S12, Adams County Coal |
1,300 MW | Withdrawn / abandoned |
| Gas project AC1-096, Pickaway County Gas |
1,277 MW | Withdrawn / abandoned |
| Gas project AD1-090, Washington County Gas |
1,260 MW | Withdrawn / abandoned |
| Gas project AB2-080, Pickaway County Gas |
1,200 MW | Withdrawn / abandoned |
| Coal project G482, Ashtabula County Coal |
1,200 MW | Withdrawn / abandoned |
| Coal project N42, Meigs County Coal |
1,200 MW | Withdrawn / abandoned |
| Gas project AE1-213, Trumbull County Gas |
1,170 MW | Withdrawn / abandoned |
| Gas project AE2-013, Trumbull County Gas |
1,170 MW | Withdrawn / abandoned |
| Gas project Y2-085, Carroll County Gas |
1,050 MW | Withdrawn / abandoned |
| Harrison Power Plant Gas |
1,050 MW | Withdrawn / abandoned |
| Racine Coal |
1,035 MW | Withdrawn / abandoned |
| Cedar Point Energy Center Gas |
955 MW | Withdrawn / abandoned |
| Gas project AD2-057, Trumbull County Gas |
940 MW | Withdrawn / abandoned |
| Other project G083, Hamilton County Other |
800 MW | Withdrawn / abandoned |
| Gas project W3-128, Meigs County Gas |
652 MW | Withdrawn / abandoned |
| Gas project AH1-724, Harrison County Gas ยท Pogona Power LLC |
650 MW | Withdrawn / abandoned |
| Gas project AD1-091, Washington County Gas |
630 MW | Withdrawn / abandoned |
| Gas project X3-051 Gas |
610 MW | Withdrawn / abandoned |
| Coal project P55, Allen County Coal |
600 MW | Withdrawn / abandoned |
| Other project G082, Hamilton County Other |
600 MW | Withdrawn / abandoned |
| Gas project Z1-018, Defiance County Gas |
591 MW | Withdrawn / abandoned |
| Gas project P02, Muskingum County Gas |
550 MW | Withdrawn / abandoned |
| Gas project AE1-119, Wood County Gas |
550 MW | Withdrawn / abandoned |
| Coal project O44, Allen County Coal |
540 MW | Withdrawn / abandoned |
| Onshore wind project AD1-103, Huron County Onshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project AC2-104, Van Wert County Onshore wind |
500 MW | Withdrawn / abandoned |
| Grange Solar Solar |
500 MW | Withdrawn / abandoned |
| Battery storage project AH1-758, Adams County Battery storage ยท Cardinal Energy Storage East, LLC |
500 MW | Withdrawn / abandoned |
| Battery storage project AH1-757, Union County Battery storage ยท Cardinal Energy Storage East, LLC |
500 MW | Withdrawn / abandoned |
| Emerson Creek Wind Farm Onshore wind |
500 MW | Withdrawn / abandoned |
| Battery storage project AH1-754, Muskingum County Battery storage ยท Cardinal Energy Storage East, LLC |
500 MW | Withdrawn / abandoned |
| Battery storage project AG2-375, Hancock County Battery storage ยท Foster Energy Storage LLC |
500 MW | Withdrawn / abandoned |
| Onshore wind project W3-005, Huron County Onshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project J208, Huron County Onshore wind |
500 MW | Withdrawn / abandoned |
| Gas project Z1-030, Lucas County Gas |
464 MW | Withdrawn / abandoned |
| Gas project Y1-036, Lake County Gas |
462 MW | Withdrawn / abandoned |
| Gas project Y1-035, Lake County Gas |
462 MW | Withdrawn / abandoned |
| Onshore wind project AD1-104, Van Wert County Onshore wind |
403 MW | Withdrawn / abandoned |
| Grange Solar Solar + storage |
400 MW | Withdrawn / abandoned |
| Battery storage project AH1-752, Stark County Battery storage ยท Cardinal Energy Storage East, LLC |
400 MW | Withdrawn / abandoned |
| Solar project AG2-105, Madison County Solar |
400 MW | Withdrawn / abandoned |
| Battery storage project AG2-376, Franklin County Battery storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project AE2-149, Pickaway County Solar + storage |
400 MW | Withdrawn / abandoned |
| Onshore wind project AD2-136, Seneca County Onshore wind |
360 MW | Withdrawn / abandoned |
| Coal project R13, Columbiana County Coal |
350 MW | Withdrawn / abandoned |
| Solar project AG2-149, Crawford County Solar ยท Wombat Solar LLC |
314 MW | Withdrawn / abandoned |
| Onshore wind project AC1-225, Van Wert County Onshore wind |
300 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)