United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

GAS Β· PJM

Cedar Point Energy Center

Cedar Point Energy Center is a 955 MW gas request withdrawn in the PJM interconnection queue, in Lucas County, Ohio, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2015 (completed)
  2. Withdrawn / abandonedSep 2023 (project stopped here)
  3. ConsentedNov 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AB1-107
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Bayshore-GM Powertrain 138 kV & Lallendorf 345kV
Location
Lucas County, Ohio
Technology
Gas: 955 MW
Total requested
955 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
22 October 2015
Agreement signed
25 November 2019
Proposed online date
November 2024
Withdrawn
September 2023

Location

Marker shows the centre of Lucas County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Lucas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem