United States βΊ Grid βΊ Interconnection queues βΊ Ohio
GAS Β· PJMOregon Energy Center
Oregon Energy Center is a 799 MW gas request built and operating in the PJM interconnection queue, in Lucas County, Ohio, connecting to ATSI.
Request details
- Queue ID
- Y1-069
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Connection point (POI)
- Bay Shore-Fostoria Central 345kV & Bayshore-Monroe 345kV
- Location
- Lucas County, Ohio
- Technology
- Gas: 799 MW
- Total requested
- 799 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 27 April 2012
- Proposed online date
- May 2017
- Came online
- June 2017
Location
Marker shows the centre of Lucas County; the queue data does not give exact sites.
Other requests in Lucas County
- Gas project H037, Lucas CountyGas Β· 135 MW Β· agreement signed
- Oregon Energy CenterGas Β· 161 MW Β· built
- Gas project AH1-690, Lucas CountyGas Β· 1,475 MW Β· withdrawn
- Cedar Point Energy CenterGas Β· 955 MW Β· withdrawn
- Gas project Z1-030, Lucas CountyGas Β· 464 MW Β· withdrawn
- Battery storage project AG1-199, Lucas CountyBattery storage Β· 300 MW Β· withdrawn
- Gas project H023, Lucas CountyGas Β· 135 MW Β· withdrawn
- FDS Coke PlantOther Β· 135 MW Β· withdrawn
- Battery storage project AG2-223, Lucas CountyBattery storage Β· 100 MW Β· withdrawn
- Solar project AG2-515, Lucas CountySolar Β· 100 MW Β· withdrawn
- Onshore wind project G754, Lucas CountyOnshore wind Β· 50.0 MW Β· withdrawn
- Solar project Y2-091, Lucas CountySolar Β· 0.3 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem