πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

ONSHORE WIND Β· PJM

Emerson Creek Wind Farm

Emerson Creek Wind Farm is a 500 MW onshore wind request withdrawn in the PJM interconnection queue, in Huron County, Ohio, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedJul 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
X1-027A_AT12
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Davis Besse-Beaver 345kV
Location
Huron County, Ohio
Technology
Wind: 500 MW
Total requested
500 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
3 March 2011
Proposed online date
April 2018
Withdrawn
July 2018

Location

Marker shows the centre of Huron County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Huron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem