United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

SOLAR + STORAGE Β· PJM

Norwalk Solar I

Norwalk Solar I is a 49.9 MW solar + storage request withdrawn in the PJM interconnection queue, in Huron County, Ohio, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2021 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-094
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Developer
Norwalk Solar, LLC
Connection point (POI)
Wells - Shinrock 69 kV I
Location
Huron County, Ohio
Technology
Solar: 49.9 MW Β· Battery
Total requested
49.9 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
30 July 2021
Proposed online date
June 2025
Withdrawn
July 2025

Location

Marker shows the centre of Huron County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Huron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem