ONSHORE WIND Β· MISO

Onshore wind project J208, Huron County

Onshore wind project J208, Huron County is a 500 MW onshore wind request withdrawn in the MISO interconnection queue, in Huron County, Ohio.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedJun 2011 (project stopped here)
  3. ConsentedJun 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J208
Grid region
MISO (Midcontinent)
Connection point (POI)
FE Davis Besse - Beaver 345 kV
Location
Huron County, Ohio
Technology
Wind: 500 MW
Total requested
500 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
3 March 2011
Agreement signed
1 June 2011
Proposed online date
December 2014
Withdrawn
June 2011

Location

Marker shows the centre of Huron County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Huron County