United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

GAS Β· PJM

Gas project AC1-096, Pickaway County

Gas project AC1-096, Pickaway County is a 1,277 MW gas request withdrawn in the PJM interconnection queue, in Pickaway County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2016 (completed)
  2. Withdrawn / abandonedFeb 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AC1-096
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Marysville-Flatlick 765kV
Location
Pickaway County, Ohio
Technology
Gas: 1,277 MW
Total requested
1,277 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
20 October 2016
Proposed online date
June 2021
Withdrawn
February 2017

Location

Marker shows the centre of Pickaway County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Pickaway County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem