SOLAR + STORAGE Β· PJM

Grange Solar

Grange Solar is a 400 MW solar + storage request withdrawn in the PJM interconnection queue, in Logan County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedFeb 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG1-003
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Marysville-Sorenson 765 kV
Location
Logan County, Ohio
Technology
Solar: 400 MW Β· Battery
Total requested
400 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study
Queue status
Withdrawn
Entered queue
20 April 2020
Proposed online date
December 2023
Withdrawn
February 2025

Location

Marker shows the centre of Logan County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Logan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem