United States βΊ Grid βΊ Interconnection queues βΊ Ohio
BATTERY STORAGE Β· PJMBattery storage project AH1-320, Logan County
Battery storage project AH1-320, Logan County is a 69.0 MW battery storage request withdrawn in the PJM interconnection queue, in Logan County, Ohio, connecting to Dayton.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-320
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dayton
- Developer
- Invenergy Storage Development LLC
- Connection point (POI)
- Blue Jacket - Kirby 138 kV
- Location
- Logan County, Ohio
- Technology
- Battery: 69.0 MW
- Total requested
- 69.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Withdrawn
- Entered queue
- 10 September 2021
- Proposed online date
- December 2025
- Withdrawn
- July 2025
Location
Marker shows the centre of Logan County; the queue data does not give exact sites.
Other requests in Logan County
- Solar project AI2-081, Logan CountySolar Β· 271 MW Β· in study
- Solar project AH2-010, Logan CountySolar Β· 100 MW Β· in study
- Cherokee Run LFOther Β· 10.0 MW Β· built
- Grange SolarSolar Β· 500 MW Β· withdrawn
- Grange SolarSolar + storage Β· 400 MW Β· withdrawn
- Grange SolarBattery storage Β· 200 MW Β· withdrawn
- Solar project AG2-013, Logan CountySolar Β· 200 MW Β· withdrawn
- Solar + storage project AH2-147, Logan CountySolar + storage Β· 119 MW Β· withdrawn
- Onshore wind project G756, Logan CountyOnshore wind Β· 101 MW Β· withdrawn
- Onshore wind project S51, Logan CountyOnshore wind Β· 99.0 MW Β· withdrawn
- Solar project AH1-198, Logan CountySolar Β· 55.0 MW Β· withdrawn
- Solar project AF1-270, Logan CountySolar Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem