πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

SOLAR Β· PJM

Solar project AG2-013, Logan County

Solar project AG2-013, Logan County is a 200 MW solar request withdrawn in the PJM interconnection queue, in Logan County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2020 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-013
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Marysville-Sorenson 765 kV
Location
Logan County, Ohio
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
16 October 2020
Proposed online date
December 2023
Withdrawn
December 2024

Location

Marker shows the centre of Logan County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Logan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem