United States βΊ Grid βΊ Interconnection queues βΊ Ohio
COAL Β· MISOCoal project G482, Ashtabula County
Coal project G482, Ashtabula County is a 1,200 MW coal request withdrawn in the MISO interconnection queue, in Ashtabula County, Ohio.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2004 (completed)
- Withdrawn / abandonedFeb 2006 (project stopped here)
- ConsentedFeb 2006 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G482
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- ATSI Perry - Ashtabula
- Location
- Ashtabula County, Ohio
- Technology
- Coal: 1,200 MW
- Total requested
- 1,200 MW
- Queue status
- Withdrawn
- Entered queue
- 19 November 2004
- Agreement signed
- 24 February 2006
- Proposed online date
- November 2006
- Withdrawn
- February 2006
Location
Marker shows the centre of Ashtabula County; the queue data does not give exact sites.
Other requests in Ashtabula County
- Geneva Renewable Energy FacilityOther Β· 6.5 MW Β· built
- Onshore wind project J124, Ashtabula CountyOnshore wind Β· 50.0 MW Β· withdrawn
- Onshore wind project W1-070A_AT4, Ashtabula CountyOnshore wind Β· 50.0 MW Β· withdrawn
- Gas project I02, Ashtabula CountyGas Β· 35.0 MW Β· withdrawn
- Solar project AG2-243, Ashtabula CountySolar Β· 20.0 MW Β· withdrawn
- Solar project AG2-244, Ashtabula CountySolar Β· 20.0 MW Β· withdrawn
- Solar project AH1-424, Ashtabula CountySolar Β· 19.2 MW Β· withdrawn
- Solar project AH2-073, Ashtabula CountySolar Β· 10.0 MW Β· withdrawn
- Solar project AH2-074, Ashtabula CountySolar Β· 10.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem