United States βΊ Grid βΊ Interconnection queues βΊ Ohio
ONSHORE WIND Β· MISOOnshore wind project J124, Ashtabula County
Onshore wind project J124, Ashtabula County is a 50.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Ashtabula County, Ohio.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2010 (completed)
- Withdrawn / abandonedJun 2011 (project stopped here)
- ConsentedJun 2011 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J124
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Ashtabula 138 kV Substation
- Location
- Ashtabula County, Ohio
- Technology
- Wind: 50.0 MW
- Total requested
- 50.0 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 20 April 2010
- Agreement signed
- 1 June 2011
- Proposed online date
- September 2011
- Withdrawn
- June 2011
Location
Marker shows the centre of Ashtabula County; the queue data does not give exact sites.
Other requests in Ashtabula County
- Geneva Renewable Energy FacilityOther Β· 6.5 MW Β· built
- Coal project G482, Ashtabula CountyCoal Β· 1,200 MW Β· withdrawn
- Onshore wind project W1-070A_AT4, Ashtabula CountyOnshore wind Β· 50.0 MW Β· withdrawn
- Gas project I02, Ashtabula CountyGas Β· 35.0 MW Β· withdrawn
- Solar project AG2-243, Ashtabula CountySolar Β· 20.0 MW Β· withdrawn
- Solar project AG2-244, Ashtabula CountySolar Β· 20.0 MW Β· withdrawn
- Solar project AH1-424, Ashtabula CountySolar Β· 19.2 MW Β· withdrawn
- Solar project AH2-073, Ashtabula CountySolar Β· 10.0 MW Β· withdrawn
- Solar project AH2-074, Ashtabula CountySolar Β· 10.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem