United States βΊ Grid βΊ Interconnection queues βΊ Ohio
BATTERY STORAGE Β· PJMBattery storage project AH1-754, Muskingum County
Battery storage project AH1-754, Muskingum County is a 500 MW battery storage request withdrawn in the PJM interconnection queue, in Muskingum County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedMay 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-754
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Developer
- Cardinal Energy Storage East, LLC
- Location
- Muskingum County, Ohio
- Technology
- Battery: 500 MW
- Total requested
- 500 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Withdrawn
- Proposed online date
- June 2029
- Withdrawn
- May 2025
Location
Marker shows the centre of Muskingum County; the queue data does not give exact sites.
Other requests in Muskingum County
- Other project AH1-661, Muskingum CountyOther Β· 10.1 MW Β· in study
- DresdenGas Β· 580 MW Β· built
- DresdenGas Β· 98.0 MW Β· built
- Conesville #5Coal Β· 5.0 MW Β· built
- Conesville #6Coal Β· 5.0 MW Β· built
- Zanesville EnergyOther Β· 0.9 MW Β· built
- Gas project P02, Muskingum CountyGas Β· 550 MW Β· withdrawn
- Solar project AC1-024, Muskingum CountySolar Β· 150 MW Β· withdrawn
- Muskingum SolarSolar Β· 150 MW Β· withdrawn
- Solar project AD2-151, Muskingum CountySolar Β· 100 MW Β· withdrawn
- Solar project AC2-054, Muskingum CountySolar Β· 10.0 MW Β· withdrawn
- Hydro project Z2-037, Muskingum CountyHydro Β· 4.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem