United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

GAS Β· PJM

Dresden

Dresden is a 580 MW gas request built and operating in the PJM interconnection queue, in Muskingum County, Ohio, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Jul 2007 (completed)
  2. ConsentedJun 2009 (completed)
  3. Construction (completed)
  4. OperatingOct 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
S101
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Ohio Central 138kV
Location
Muskingum County, Ohio
Technology
Gas: 580 MW
Total requested
580 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
31 July 2007
Agreement signed
19 June 2009
Proposed online date
October 2011
Came online
October 2011

Location

Marker shows the centre of Muskingum County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Muskingum County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem