Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6711.8 GW
Active in queue5,391 MW28 requests
Agreement signed50.0 MW1 requests
Withdrawn6711.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

67 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2595, Hinds County
Solar
650 MWWithdrawn / abandoned Hinds, MSMISO Sep 2022target 2026
Solar project J2594, Hinds County
Solar
650 MWWithdrawn / abandoned Hinds, MSMISO Sep 2022target 2026
Onshore wind project J2698, Choctaw County
Onshore wind
500 MWWithdrawn / abandoned Choctaw, MSMISO Sep 2022target 2028
Other project J2692, Choctaw County
Other
500 MWWithdrawn / abandoned Choctaw, MSMISO Sep 2022target 2028
Solar + storage project J2856, Jefferson County
Solar + storage
500 MWWithdrawn / abandoned Jefferson, MSMISO Sep 2022target 2024
Onshore wind project J2591, Choctaw County
Onshore wind
500 MWWithdrawn / abandoned Choctaw, MSMISO Sep 2022target 2028
Solar + storage project J2900, Amite County
Solar + storage
400 MWWithdrawn / abandoned Amite, MSMISO Sep 2022target 2026
Solar + storage project J3105, Amite County
Solar + storage
400 MWWithdrawn / abandoned Amite, MSMISO Sep 2022target 2025
Solar + storage project 520, Panola County
Solar + storage
400 MWWithdrawn / abandoned Panola, MSSoutheast Sep 2022target 2024
Solar project J2971, Covington County
Solar
280 MWWithdrawn / abandoned Covington, MSMISO Sep 2022target 2026
Onshore wind project J2964, Tallahatchie County
Onshore wind
220 MWWithdrawn / abandoned Tallahatchie, MSMISO Sep 2022target 2025
Solar + storage project J3115, Sharkey County
Solar + storage
216 MWWithdrawn / abandoned Sharkey, MSMISO Sep 2022target 2026
Solar project J3126, Washington County
Solar
200 MWWithdrawn / abandoned Washington, MSMISO Sep 2022target 2026
Solar + storage project 508, Choctaw County
Solar + storage
200 MWWithdrawn / abandoned Choctaw, MSSoutheast Jul 2022target 2026
Solar project 502, Noxubee County
Solar
200 MWWithdrawn / abandoned Noxubee, MSSoutheast May 2022
Solar project J2406, Madison County
Solar
200 MWWithdrawn / abandoned Madison, MSMISO Sep 2022target 2026
Solar + storage project J2898, Amite County
Solar + storage
200 MWWithdrawn / abandoned Amite, MSMISO Sep 2022target 2026
Solar + storage project J2827, Hinds County
Solar + storage
200 MWWithdrawn / abandoned Hinds, MSMISO Sep 2022target 2025
Solar + storage project 506, Alcorn County
Solar + storage
186 MWWithdrawn / abandoned Alcorn, MSSoutheast Jun 2022
Solar + storage project J3108, Jasper County
Solar + storage
180 MWWithdrawn / abandoned Jasper, MSMISO Sep 2022target 2026
Solar + storage project J2321, Lamar County
Solar + storage
180 MWWithdrawn / abandoned Lamar, MSMISO May 2022target 2025
Battery storage project J2992, Perry County
Battery storage
160 MWWithdrawn / abandoned Perry, MSMISO Sep 2022target 2025
Solar + storage project J3097, Amite County
Solar + storage
150 MWWithdrawn / abandoned Amite, MSMISO Sep 2022target 2025
Solar project J2939, Tunica County
Solar
150 MWWithdrawn / abandoned Tunica, MSMISO Sep 2022target 2025
Solar project J2558, Sunflower County
Solar
150 MWWithdrawn / abandoned Sunflower, MSMISO Sep 2022target 2027
Solar + storage project J2803, Carroll County
Solar + storage
150 MWWithdrawn / abandoned Carroll, MSMISO Sep 2022target 2027
Solar project J2432, Tunica County
Solar
150 MWWithdrawn / abandoned Tunica, MSMISO Sep 2022target 2026
Solar + storage project IC-1031, Jasper County
Solar + storage
150 MWWithdrawn / abandoned Jasper, MSSoutheast Mar 2022target 2025
Solar + storage project J2857, Tunica County
Solar + storage
150 MWWithdrawn / abandoned Tunica, MSMISO Sep 2022target 2024
Solar project J3201, Walthall County
Solar
148 MWWithdrawn / abandoned Walthall, MSMISO Sep 2022target 2026
Solar + storage project J2727, Holmes County
Solar + storage
140 MWWithdrawn / abandoned Holmes, MSMISO Sep 2022target 2025
Solar project J2560, Sunflower County
Solar
130 MWWithdrawn / abandoned Sunflower, MSMISO Sep 2022target 2027
Solar + storage project J2903, Lincoln County
Solar + storage
130 MWWithdrawn / abandoned Lincoln, MSMISO Sep 2022target 2025
Solar project IC-1089, Perry County
Solar
125 MWWithdrawn / abandoned Perry, MSSoutheast Nov 2022target 2027
Solar project IC-1029, Lamar County
Solar
125 MWWithdrawn / abandoned Lamar, MSSoutheast Mar 2022target 2026
Solar project J2768, Bolivar County
Solar
120 MWWithdrawn / abandoned Bolivar, MSMISO Sep 2022target 2026
Solar + storage project J3072, Wilkinson County
Solar + storage
120 MWWithdrawn / abandoned Wilkinson, MSMISO Sep 2022target 2024
Solar + storage project J3092, Bolivar County
Solar + storage
115 MWWithdrawn / abandoned Bolivar, MSMISO Sep 2022target 2026
Solar project J2358, Madison County
Solar
114 MWWithdrawn / abandoned Madison, MSMISO Sep 2022target 2024
Solar + storage project IC-1045, Stone County
Solar + storage
110 MWWithdrawn / abandoned Stone, MSSoutheast Jul 2022
Solar project J2483, Amite County
Solar
105 MWWithdrawn / abandoned Amite, MSMISO Sep 2022target 2025
Solar + storage project J3062, Hinds County
Solar + storage
100 MWWithdrawn / abandoned Hinds, MSMISO Sep 2022target 2025
Solar + storage project J2736, Bolivar County
Solar + storage
100 MWWithdrawn / abandoned Bolivar, MSMISO Sep 2022target 2025
Solar project J2940, Sharkey County
Solar
100 MWWithdrawn / abandoned Sharkey, MSMISO Sep 2022target 2025
Solar project J2741, Sunflower County
Solar
100 MWWithdrawn / abandoned Sunflower, MSMISO Sep 2022target 2026
Solar project J3150, Panola County
Solar
100 MWWithdrawn / abandoned Panola, MSMISO Sep 2022target 2027
Solar + storage project J2905, Washington County
Solar + storage
100 MWWithdrawn / abandoned Washington, MSMISO Sep 2022target 2025
Solar project J2428, Coahoma County
Solar
100 MWWithdrawn / abandoned Coahoma, MSMISO Sep 2022target 2026
Solar project J2370, Hinds County
Solar
100 MWWithdrawn / abandoned Hinds, MSMISO Sep 2022target 2024
Solar project J2391, Tallahatchie County
Solar
100 MWWithdrawn / abandoned Tallahatchie, MSMISO Sep 2022target 2026
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)