SOLAR + STORAGE Β· MISO

Solar + storage project J3072, Wilkinson County

Solar + storage project J3072, Wilkinson County is a 120 MW solar + storage request withdrawn in the MISO interconnection queue, in Wilkinson County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3072
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI, LLC.
Connection point (POI)
Woodviille - Centreville 115 kV
Location
Wilkinson County, Mississippi
Technology
Solar: 120 MW Β· Battery
Total requested
120 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
14 September 2022
Proposed online date
December 2024
Withdrawn
March 2023

Location

Marker shows the centre of Wilkinson County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Other requests in Wilkinson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem