United States βΊ Grid βΊ Interconnection queues βΊ Mississippi
SOLAR + STORAGE Β· SOUTHEASTSolar + storage project IC-1045, Stone County
Solar + storage project IC-1045, Stone County is a 110 MW solar + storage request withdrawn in the Southeast interconnection queue, in Stone County, Mississippi, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2022 (completed)
- Withdrawn / abandonedSep 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-1045
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Gulfport Landon - Wiggins IP 115 kV Line
- Location
- Stone County, Mississippi
- Technology
- Solar: 110 MW Β· Battery
- Total requested
- 110 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 22 July 2022
- Withdrawn
- September 2022
Location
Marker shows the centre of Stone County; the queue data does not give exact sites.
Power plants in Mississippi Β· Transmission lines in Mississippi
Other requests in Stone County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem