United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
OCTARY USA Β· INTERCONNECTION QUEUESProjects with signed interconnection agreements in Kentucky
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project LGE-GIS-2009-004, Trimble County Gas |
785 MW | Agreement signed |
| Gas project 417, Muhlenberg County Gas |
780 MW | Agreement signed |
| Gas project LGE-GIS-2013-001, Jefferson County Gas |
691 MW | Agreement signed |
| Gas project LGE-GIS-2010-001, Jefferson County Gas |
690 MW | Agreement signed |
| Gas project LGE-GIS-2022-003, Jefferson County Gas |
660 MW | Agreement signed |
| Gas project LGE-GIS-2023-002, Mercer County Gas |
660 MW | Agreement signed |
| Solar project J1466, Henderson County Solar |
250 MW | Agreement signed |
| Goldfinch Solar Solar Β· Goldfinch Solar, LLC |
250 MW | Agreement signed |
| Lynn Bark Energy Center Solar |
200 MW | Agreement signed |
| Fleming Solar Solar Β· AEUG Fleming Solar, LLC |
189 MW | Agreement signed |
| Solar project 364, Logan County Solar |
173 MW | Agreement signed |
| Solar project J1450, Webster County Solar |
150 MW | Agreement signed |
| Exie Solar Solar Β· Exie Solar, LLC |
150 MW | Agreement signed |
| Solar project LGE-GIS-2021-010, Marion County Solar |
120 MW | Agreement signed |
| Solar + storage project LGE-GIS-2021-020, Mccracken County Solar + storage |
120 MW | Agreement signed |
| Battery storage project LGE-GIS-2021-013, Hardin County Battery storage |
120 MW | Agreement signed |
| Summer Shade Solar Solar + storage Β· Summer Shade Solar, LLC |
106 MW | Agreement signed |
| Threeforks Energy Storage Battery storage |
100 MW | Agreement signed |
| Solar project LGE-GIS-2019-025, Mercer County Solar |
99.0 MW | Agreement signed |
| Northern Bobwhite Solar Solar |
96.0 MW | Agreement signed |
| Gas project LGE-GIS-2024-006, Jefferson County Gas |
94.0 MW | Agreement signed |
| Solar project LGE-GIS-2017-002, Lyon County Solar |
86.0 MW | Agreement signed |
| Stonecrop Solar Solar Β· CPV Stonecrop Solar, LLC |
82.0 MW | Agreement signed |
| Bright Mountain Solar Solar |
80.0 MW | Agreement signed |
| Gas project LGE-GIS-2024-002, Hopkins County Gas |
75.0 MW | Agreement signed |
| Blue Moon Solar Solar |
70.0 MW | Agreement signed |
| Solar project 388, Simpson County Solar |
69.0 MW | Agreement signed |
| Mt Olive Creek Solar Solar |
60.0 MW | Agreement signed |
| Horseshoe Bend Solar Solar |
60.0 MW | Agreement signed |
| Flat Run Solar Solar |
55.0 MW | Agreement signed |
| Barrelhead Solar Β· Barrelhead Solar, LLC |
54.0 MW | Agreement signed |
| Grassy Plains Solar |
40.0 MW | Agreement signed |
| Hydro project LGE-GIS-2011-003, Jefferson County Hydro |
21.0 MW | Agreement signed |
| Solar project LGE-GIS-2014-001, Mercer County Solar |
10.0 MW | Agreement signed |
| Solar project LGE-GIS-2016-001, Clark County Solar |
9.0 MW | Agreement signed |
| Hydro project LGE-GIS-2011-005, Mercer County Hydro |
6.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- Southeast (non-ISO utilities)19 Β· 5,268 MW
- PJM (Mid-Atlantic, Midwest)15 Β· 1,592 MW
- MISO (Midcontinent)2 Β· 400 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)