United States › Grid › Interconnection queues › Kentucky
SOLAR · SOUTHEASTSolar project LGE-GIS-2021-010, Marion County
Solar project LGE-GIS-2021-010, Marion County is a 120 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Marion County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.
Queue statusConsented
- PlanningQueued Mar 2021 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- LGE-GIS-2021-010
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Louisville Gas & Electric and Kentucky Utilities Energy
- Connection point (POI)
- Lebanon 138 kV bus
- Location
- Marion County, Kentucky
- Technology
- Solar: 120 MW
- Total requested
- 120 MW
- Service type
- Network resource (NRIS)
- Study phase
- LGIA signed
- Queue status
- Active
- Entered queue
- 22 March 2021
- Proposed online date
- June 2026
Location
Marker shows the centre of Marion County; the queue data does not give exact sites.
Other requests in Marion County
- Northern Bobwhite SolarSolar · 96.0 MW · agreement signed
- Solar project AG2-298, Marion CountySolar · 35.0 MW · in study
- Solar project AH2-263, Marion CountySolar · 25.8 MW · in study
- Solar project AI2-349, Marion CountySolar · 11.0 MW · in study
- Solar project AG1-488, Marion CountySolar · 70.0 MW · withdrawn
- Solar project AH1-532, Marion CountySolar · 37.8 MW · withdrawn
- Solar project AG2-512, Marion CountySolar · 17.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem