Solar project AG1-488, Marion County

Solar project AG1-488, Marion County is a 70.0 MW solar request withdrawn in the PJM interconnection queue, in Marion County, Kentucky, connecting to EKPC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2020 (completed)
  2. Withdrawn / abandonedJun 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG1-488
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
EKPC
Developer
BrightNight, LLC
Connection point (POI)
Marion Co 161 kV
Location
Marion County, Kentucky
Technology
Solar: 70.0 MW
Total requested
70.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
30 September 2020
Proposed online date
September 2022
Withdrawn
June 2024

Location

Marker shows the centre of Marion County; the queue data does not give exact sites.

Power plants in Kentucky Β· Transmission lines in Kentucky

Other requests in Marion County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem