Solar project 364, Logan County

Solar project 364, Logan County is a 173 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Logan County, Kentucky, connecting to Tennessee Valley Authority.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
364
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tennessee Valley Authority
Connection point (POI)
Springfield - Logan Aluminum 161-kV TL
Location
Logan County, Kentucky
Technology
Solar: 173 MW
Total requested
173 MW
Study phase
IA Executed
Queue status
Active
Entered queue
2 April 2019
Proposed online date
August 2024

Location

Marker shows the centre of Logan County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky

Other requests in Logan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem