United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Southeast (non-ISO utilities) (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6312.7 GW
Active in queue12.7 GW63 requests
Agreement signed1,908 MW12 requests
Withdrawn12316.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

63 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 489, Roane County
Gas
1,689 MWIn study Roane, TNSoutheast Dec 2021target 2026
Gas project 483, Stewart County
Gas
1,600 MWIn study Stewart, TNSoutheast Oct 2021target 2025
Solar + storage project IC-942, Glynn County
Solar + storage
1,200 MWPaused / redesign Glynn, GASoutheast Mar 2021target 2025
Battery storage project IC-974, Fulton County
Battery storage
600 MWPaused / redesign Fulton, GASoutheast Jul 2021target 2025
Bull Creek (Osceola Generating Station)
Gas
555 MWAgreement signed Osceola, FLSoutheast Sep 2021target 2025
Solar + storage project LGE-GIS-2021-008, Clark County
Solar + storage
500 MWPaused / redesign Clark, INSoutheast Mar 2021target 2026
Solar project IC-950, Mcduffie County
Solar
250 MWAgreement signed Mcduffie, GASoutheast Apr 2021target 2024
Solar project IC-986, Lamar County
Solar
250 MWPaused / redesign Lamar, MSSoutheast Oct 2021target 2025
Solar project IC-972, Jasper County
Solar
250 MWPaused / redesign Jasper, GASoutheast Jul 2021target 2024
Solar project 171, Williamsburg County
Solar
249 MWUnder construction Williamsburg, SCSoutheast Oct 2021target 2028
Battery storage project 292, Pinellas County
Battery storage Β· Duke Energy Florida, LLC
225 MWUnder construction Pinellas, FLSoutheast Apr 2021target 2025
Solar project IC-990, Toombs County
Solar
200 MWPaused / redesign Toombs, GASoutheast Oct 2021target 2025
Fairboro Solar
Solar
200 MWIn study Ware, GASoutheast Dec 2021target 2023
Solar + storage project LGE-GIS-2021-009, Hardin County
Solar + storage
200 MWPaused / redesign Hardin, KYSoutheast Mar 2021target 2026
Solar project 466, Clay County
Solar
200 MWAgreement signed Clay, MSSoutheast Feb 2021target 2028
Solar project IC-989, Johnson County
Solar
150 MWPaused / redesign Johnson, GASoutheast Oct 2021target 2025
Talbot Solar
Solar
150 MWIn study Talbot, GASoutheast Dec 20212023
Crossroads Solar
Solar + storage
150 MWIn study Liberty, GASoutheast Jun 2021target 2024
Solar + storage project IC-964, Emanuel County
Solar + storage
150 MWPaused / redesign Emanuel, GASoutheast Jun 2021target 2025
Dellwood Solar
Solar + storage
150 MWIn study Emanuel, GASoutheast May 20212023
Cherry Tree Solar
Solar + storage
150 MWIn study Washington, GASoutheast Dec 2021target 2025
Solar + storage project IC-1006, Liberty County
Solar + storage
150 MWPaused / redesign Liberty, GASoutheast Dec 2021target 2026
Solar + storage project IC-966, Decatur County
Solar + storage
130 MWAgreement signed Decatur, GASoutheast Jun 2021target 2024
Solar + storage project 469, Henderson County
Solar + storage
125 MWAgreement signed Henderson, TNSoutheast Mar 2021target 2028
Solar project IC-988, Oglethorpe County
Solar
120 MWPaused / redesign Oglethorpe, GASoutheast Oct 2021target 2025
Solar project LGE-GIS-2021-010, Marion County
Solar
120 MWAgreement signed Marion, KYSoutheast Mar 2021target 2026
Solar + storage project LGE-GIS-2021-020, Mccracken County
Solar + storage
120 MWAgreement signed Mccracken, KYSoutheast Jun 2021target 2026
Solar project LGE-GIS-2021-007, Mccracken County
Solar
120 MWPaused / redesign Mccracken, KYSoutheast Mar 2021target 2026
SR Rochelle Solar
Solar
120 MWUnder construction Wilcox, GASoutheast Dec 2021target 2026
Battery storage project LGE-GIS-2021-013, Hardin County
Battery storage
120 MWAgreement signed Hardin, KYSoutheast Mar 2021target 2028
Solar + storage project LGE-GIS-2021-018, Bath County
Solar + storage
110 MWPaused / redesign Bath, KYSoutheast May 2021target 2027
Solar project 482, Cumberland County
Solar
110 MWAgreement signed Cumberland, TNSoutheast Oct 2021target 2027
Solar + storage project LGE-GIS-2021-017, Mason County
Solar + storage
100 MWPaused / redesign Mason, KYSoutheast Apr 2021target 2026
Solar project LGE-GIS-2021-019, Boyle County
Solar
100 MWPaused / redesign Boyle, KYSoutheast May 2021target 2027
Solar project IC-1005, Burke County
Solar
100 MWPaused / redesign Burke, GASoutheast Dec 2021target 2026
Solar + storage project IC-980, Oglethorpe County
Solar + storage
100 MWPaused / redesign Oglethorpe, GASoutheast Aug 2021target 2024
Onshore wind project GI-96, Lincoln County
Onshore wind
97.5 MWAgreement signed Lincoln, OKSoutheast Oct 2021target 2026
Long Cane Solar
Solar + storage
80.0 MWIn study Troup, GASoutheast Jul 2021target 2024
Solar + storage project IC-999, Baldwin County
Solar + storage
80.0 MWPaused / redesign Baldwin, ALSoutheast Dec 2021target 2026
Solar + storage project IC-971, Lowndes County
Solar + storage
80.0 MWPaused / redesign Lowndes, ALSoutheast Jul 2021target 2026
Solar + storage project IC-954, Conecuh County
Solar + storage
80.0 MWPaused / redesign Conecuh, ALSoutheast Apr 2021target 2026
Solar + storage project IC-997, Baldwin County
Solar + storage
80.0 MWPaused / redesign Baldwin, ALSoutheast Dec 2021target 2026
Solar + storage project IC-1000, Baldwin County
Solar + storage
80.0 MWPaused / redesign Baldwin, ALSoutheast Dec 2021target 2026
Solar + storage project IC-979, Conecuh County
Solar + storage
80.0 MWPaused / redesign Conecuh, ALSoutheast Aug 2021target 2026
Solar project IC-1001, Early County
Solar
80.0 MWPaused / redesign Early, GASoutheast Dec 2021target 2025
Solar project IC-943, Talladega County
Solar
80.0 MWPaused / redesign Talladega, ALSoutheast Mar 2021target 2025
Solar project IC-975, Dale County
Solar
80.0 MWPaused / redesign Dale, ALSoutheast Jul 2021target 2025
Solar project IC-1002, Decatur County
Solar
78.0 MWPaused / redesign Decatur, GASoutheast Dec 2021target 2025
Solar project 167, Darlington County
Solar
75.0 MWPaused / redesign Darlington, SCSoutheast Oct 2021target 2025
Solar project 925531, Williamsburg County
Solar
74.9 MWUnder construction Williamsburg, SCSoutheast Jun 2021target 2026
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)