United States › Grid › Interconnection queues › Georgia
SOLAR + STORAGE · SOUTHEASTSolar + storage project IC-1006, Liberty County
Solar + storage project IC-1006, Liberty County is a 150 MW solar + storage request suspended in the Southeast interconnection queue, in Liberty County, Georgia, connecting to Southern Company.
Queue statusPaused / redesign
- PlanningQueued Dec 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- IC-1006
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Ludowici Primary - Riceboro 115 kV Line
- Location
- Liberty County, Georgia
- Technology
- Solar: 150 MW · Battery
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Queue status
- Suspended
- Entered queue
- 23 December 2021
- Proposed online date
- January 2026
Location
Marker shows the centre of Liberty County; the queue data does not give exact sites.
Other requests in Liberty County
- Solar + storage project IC-903, Liberty CountySolar + storage · 13.0 MW · agreement signed
- Crossroads SolarSolar + storage · 150 MW · in study
- Fort Stewart SolarSolar · 29.3 MW · built
- Solar + storage project IC-900, Liberty CountySolar + storage · 90.0 MW · withdrawn
- Solar project IC-420, Liberty CountySolar · 16.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem