πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

SOLAR + STORAGE Β· SOUTHEAST

Solar + storage project IC-900, Liberty County

Solar + storage project IC-900, Liberty County is a 90.0 MW solar + storage request withdrawn in the Southeast interconnection queue, in Liberty County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2020 (completed)
  2. Withdrawn / abandonedMay 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-900
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Riceboro β€šΓ„Γ¬ Interstate Paper CU115 kV Line (RADIAL)
Location
Liberty County, Georgia
Technology
Solar: 90.0 MW Β· Battery
Total requested
90.0 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
26 August 2020
Withdrawn
May 2021

Location

Marker shows the centre of Liberty County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Liberty County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem