Battery storage project AI2-457, Charles County Battery storage |
1,122 MW | In study |
Charles, MD | PJM |
Mar 2023 | target 2027 |
Battery storage project AH1-716, James City County Battery storage ยท Cardinal Energy Storage East, LLC |
650 MW | In study |
James City, VA | PJM |
Apr 2025 | |
Battery storage project AH1-725, Harford County Battery storage ยท Cardinal Energy Storage East, LLC |
500 MW | In study |
Harford, MD | PJM |
Apr 2025 | |
Fourth Quarter Battery storage ยท Fourth Quarter BESS, LLC |
500 MW | Agreement signed |
Montgomery, MD | PJM |
Oct 2020 | target 2030 |
Battery storage project AH2-416, Livingston County Battery storage |
450 MW | In study |
Livingston, IL | PJM |
Mar 2022 | target 2026 |
Battery storage project AI1-022, Huntington County Battery storage |
450 MW | In study |
Huntington, IN | PJM |
Apr 2022 | target 2026 |
Battery storage project AH1-727, Loudoun County Battery storage ยท Cardinal Energy Storage East, LLC |
425 MW | In study |
Loudoun, VA | PJM |
Apr 2025 | |
Battery storage project AH2-333, Salem County Battery storage |
415 MW | In study |
Salem, NJ | PJM |
Mar 2022 | target 2025 |
Battery storage project AG2-545, Mchenry County Battery storage ยท Monarch Grid, LLC |
400 MW | In study |
Mchenry, IL | PJM |
Mar 2025 | target 2024 |
Battery storage project AJ1-012, Lake County Battery storage |
354 MW | In study |
Lake, IL | PJM |
May 2023 | target 2027 |
Battery storage project AH2-414, Huntington County Battery storage |
350 MW | In study |
Huntington, IN | PJM |
Mar 2022 | target 2026 |
Battery storage project AJ1-011, Lake County Battery storage |
328 MW | In study |
Lake, IL | PJM |
May 2023 | target 2027 |
Battery storage project AH2-133, City Of Chesapeake County Battery storage |
300 MW | In study |
City Of Chesapeake, VA | PJM |
Mar 2022 | target 2027 |
Battery storage project AI1-024, Mclean County Battery storage |
300 MW | In study |
Mclean, IL | PJM |
Apr 2022 | target 2026 |
Battery storage project AH1-260, Camden County Battery storage ยท Haddy Energy Storage LLC |
300 MW | In study |
Camden, NJ | PJM |
Jan 2025 | target 2025 |
Battery storage project AI1-017, Surry County Battery storage |
300 MW | In study |
Surry, VA | PJM |
Apr 2022 | target 2026 |
Battery storage project AH2-334, Camden County Battery storage |
300 MW | In study |
Camden, NJ | PJM |
Mar 2022 | target 2025 |
Battery storage project AH2-415, Livingston County Battery storage |
300 MW | In study |
Livingston, IL | PJM |
Mar 2022 | target 2026 |
Battery storage project AI1-018, Spotsylvania County Battery storage |
300 MW | In study |
Spotsylvania, VA | PJM |
Apr 2022 | target 2026 |
Battery storage project AI1-187, Hunterdon County Battery storage |
280 MW | In study |
Hunterdon, NJ | PJM |
Sep 2022 | target 2027 |
Battery storage project AJ1-014, Will County Battery storage |
260 MW | In study |
Will, IL | PJM |
May 2023 | target 2027 |
Battery storage project AI1-149, Mchenry County Battery storage |
250 MW | In study |
Mchenry, IL | PJM |
Sep 2022 | target 2025 |
Battery storage project AI2-068, Monmouth County Battery storage |
250 MW | In study |
Monmouth, NJ | PJM |
Feb 2023 | target 2026 |
Battery storage project AJ1-013, Will County Battery storage |
250 MW | In study |
Will, IL | PJM |
May 2023 | target 2027 |
Battery storage project AI1-167, Clermont County Battery storage |
250 MW | In study |
Clermont, OH | PJM |
Sep 2022 | target 2028 |
Woods Landing Energy Storage Battery storage |
250 MW | Agreement signed |
Atlantic, NJ | PJM |
Mar 2020 | target 2030 |
Battery storage project AG2-360, Smyth County Battery storage ยท Laurel Creek Energy Storage LLC |
250 MW | In study |
Smyth, VA | PJM |
Feb 2025 | target 2024 |
Battery storage project AI2-069, Monmouth County Battery storage |
250 MW | In study |
Monmouth, NJ | PJM |
Feb 2023 | target 2026 |
Battery storage project AI1-154, Will County Battery storage |
230 MW | In study |
Will, IL | PJM |
Sep 2022 | target 2027 |
Battery storage project AH2-421, Grundy County Battery storage |
230 MW | In study |
Grundy, IL | PJM |
Mar 2022 | target 2025 |
Battery storage project AI1-185, Augusta County Battery storage |
210 MW | In study |
Augusta, VA | PJM |
Sep 2022 | target 2027 |
Prospect Power Battery storage |
200 MW | Agreement signed |
Rockingham, VA | PJM |
May 2019 | target 2026 |
Flint Grid Battery storage |
200 MW | Agreement signed |
Licking, OH | PJM |
Jul 2019 | target 2027 |
Battery storage project AG2-329, Wyandot County Battery storage ยท Wombat Solar LLC |
200 MW | In study |
Wyandot, OH | PJM |
Mar 2025 | target 2024 |
Battery storage project AH2-102, Franklin County Battery storage |
200 MW | In study |
Franklin, VA | PJM |
Jan 2022 | target 2026 |
Battery storage project AH2-378A, Gloucester County Battery storage |
200 MW | In study |
Gloucester, NJ | PJM |
Mar 2022 | target 2025 |
Battery storage project AH2-051, New Castle County Battery storage |
200 MW | In study |
New Castle, DE | PJM |
Dec 2021 | target 2025 |
Hudson Energy Storage Facility Battery storage |
200 MW | Agreement signed |
Hudson, NJ | PJM |
Sep 2019 | target 2028 |
Battery storage project AH1-263, Spotsylvania County Battery storage ยท Scarlet Energy Storage LLC |
200 MW | In study |
Spotsylvania, VA | PJM |
Feb 2025 | target 2025 |
Battery storage project AH2-265, Charles County Battery storage |
200 MW | In study |
Charles, MD | PJM |
Mar 2022 | target 2026 |
Battery storage project AI1-013, Charles City County Battery storage |
200 MW | In study |
Charles City, VA | PJM |
Apr 2022 | target 2026 |
Battery storage project AH2-103, Fayette County Battery storage |
200 MW | In study |
Fayette, PA | PJM |
Feb 2022 | target 2026 |
Riverbank Energy Battery storage ยท Lincoln Reserve Energy, LLC |
200 MW | In study |
Cook, IL | PJM |
Mar 2020 | target 2024 |
Battery storage project AH2-347, St. Joseph County Battery storage |
200 MW | In study |
St. Joseph, IN | PJM |
Mar 2022 | target 2025 |
Battery storage project AI1-023, Mclean County Battery storage |
200 MW | In study |
Mclean, IL | PJM |
Apr 2022 | target 2026 |
Battery storage project AG2-544, Mchenry County Battery storage ยท Monarch Grid, LLC |
200 MW | In study |
Mchenry, IL | PJM |
Mar 2025 | target 2024 |
Battery storage project AH2-423, Calvert County Battery storage |
180 MW | In study |
Calvert, MD | PJM |
Mar 2022 | target 2025 |
Battery storage project AH2-259, Kendall County Battery storage |
172 MW | In study |
Kendall, IL | PJM |
Mar 2022 | target 2024 |
Battery storage project AH2-204, Stephenson County Battery storage |
170 MW | In study |
Stephenson, IL | PJM |
Mar 2022 | target 2026 |
Lamberton Road Battery Battery storage |
170 MW | Agreement signed |
Mercer, NJ | PJM |
Sep 2019 | target 2027 |