United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in PJM (Mid-Atlantic, Midwest) (2010 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project V4-074, Hancock County Onshore wind |
1,000 MW | Withdrawn / abandoned |
| Gas project W1-034, Prince George's County Gas |
750 MW | Withdrawn / abandoned |
| Gas project W1-035, Lawrence County Gas |
750 MW | Withdrawn / abandoned |
| Gas project W4-021, Middlesex County Gas |
738 MW | Withdrawn / abandoned |
| Gas project W3-128, Meigs County Gas |
652 MW | Withdrawn / abandoned |
| Gas project W2-024, Middlesex County Gas |
625 MW | Withdrawn / abandoned |
| Gas project W2-023, Middlesex County Gas |
625 MW | Withdrawn / abandoned |
| Gas project W1-073, Caroline County Gas |
612 MW | Withdrawn / abandoned |
| Gas project W1-074, Fauquier County Gas |
610 MW | Withdrawn / abandoned |
| Gas project W4-024, Hudson County Gas |
550 MW | Withdrawn / abandoned |
| Other project W3-065 Other |
500 MW | Withdrawn / abandoned |
| Offshore wind project W3-043, City Of Virginia Beach County Offshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project W3-005, Huron County Onshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project W2-046, Livingston County Onshore wind |
450 MW | Withdrawn / abandoned |
| Gas project W3-172, New Castle County Gas |
402 MW | Withdrawn / abandoned |
| Deepwater Gas |
371 MW | Withdrawn / abandoned |
| Nuclear project W1-040, Lasalle County Nuclear |
350 MW | Withdrawn / abandoned |
| New Jersey Offshore Wind Project Offshore wind |
348 MW | Withdrawn / abandoned |
| Onshore wind project W1-030, Ford County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project W1-031, Ford County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project W3-013, Miami County Onshore wind |
300 MW | Withdrawn / abandoned |
| Hales Lake Energy Center Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project W3-014, Crawford County Onshore wind |
300 MW | Withdrawn / abandoned |
| Gas project W4-023, Hudson County Gas |
300 MW | Withdrawn / abandoned |
| Onshore wind project W3-012, Hancock County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project W3-011, Hancock County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project W3-053, Washington County Onshore wind |
260 MW | Withdrawn / abandoned |
| West Deptford Energy Station Gas |
235 MW | Withdrawn / abandoned |
| Gas project W3-173, New Castle County Gas |
218 MW | Withdrawn / abandoned |
| Onshore wind project W3-046, Mason County Onshore wind |
208 MW | Withdrawn / abandoned |
| Onshore wind project W3-052, Woodford County Onshore wind |
200 MW | Withdrawn / abandoned |
| Long Prairie Wind I, LLC Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project W4-021A, Richland County Onshore wind |
200 MW | Withdrawn / abandoned |
| Gas project W3-174, Salem County Gas |
194 MW | Withdrawn / abandoned |
| Onshore wind project W3-085, Crawford County Onshore wind |
185 MW | Withdrawn / abandoned |
| Onshore wind project W4-006, Defiance County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project W3-019, Currituck County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project W2-068, Mercer County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project W3-022, Schuylkill County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project W3-054, Tyrrell County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project W3-024, Whitley County Onshore wind |
149 MW | Withdrawn / abandoned |
| Gas project W1-058A_DK1, Butler County Gas |
135 MW | Withdrawn / abandoned |
| Solar project W1-051, Franklin County Solar |
130 MW | Withdrawn / abandoned |
| Onshore wind project W3-060, Noble County Onshore wind |
120 MW | Withdrawn / abandoned |
| Onshore wind project W4-012, Elk County Onshore wind |
120 MW | Withdrawn / abandoned |
| Onshore wind project W3-023, Schuylkill County Onshore wind |
120 MW | Withdrawn / abandoned |
| Onshore wind project W2-044, Whitley County Onshore wind |
101 MW | Withdrawn / abandoned |
| Greenfield Wind Farm Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project W2-007, Putnam County Onshore wind |
100 MW | Withdrawn / abandoned |
| Solar project W4-022, Adams County Solar |
100 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)302 Β· 22.6 GW
- PJM (Mid-Atlantic, Midwest)361 Β· 21.6 GW
- CAISO (California)168 Β· 19.1 GW
- Southeast (non-ISO utilities)18 Β· 11.1 GW
- MISO (Midcontinent)72 Β· 10.9 GW
- SPP (Southwest Power Pool)50 Β· 9,058 MW
- ERCOT (Texas)28 Β· 3,689 MW
- ISO-NE (New England)12 Β· 1,337 MW
- NYISO (New York)5 Β· 1,285 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)