ONSHORE WIND Β· PJMOnshore wind project W3-060, Noble County
Onshore wind project W3-060, Noble County is a 120 MW onshore wind request withdrawn in the PJM interconnection queue, in Noble County, Indiana, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2010 (completed)
- Withdrawn / abandonedNov 2011 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- W3-060
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Kendallville 138kV
- Location
- Noble County, Indiana
- Technology
- Wind: 120 MW
- Total requested
- 120 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 13 September 2010
- Proposed online date
- November 2012
- Withdrawn
- November 2011
Location
Marker shows the centre of Noble County; the queue data does not give exact sites.
Other requests in Noble County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem