United States βΊ Grid βΊ Interconnection queues βΊ Ohio
ONSHORE WIND Β· PJMOnshore wind project W3-013, Miami County
Onshore wind project W3-013, Miami County is a 300 MW onshore wind request withdrawn in the PJM interconnection queue, in Miami County, Ohio, connecting to Dayton.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2010 (completed)
- Withdrawn / abandonedMar 2011 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- W3-013
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dayton
- Connection point (POI)
- Miami
- Location
- Miami County, Ohio
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 10 August 2010
- Proposed online date
- December 2014
- Withdrawn
- March 2011
Location
Marker shows the centre of Miami County; the queue data does not give exact sites.
Other requests in Miami County
- Solar project AI2-159, Miami CountySolar Β· 43.5 MW Β· in study
- Solar project AH2-216, Miami CountySolar Β· 200 MW Β· withdrawn
- Solar project AG2-628, Miami CountySolar Β· 200 MW Β· withdrawn
- Eldean SolarSolar Β· 178 MW Β· withdrawn
- Battery storage project AH2-221, Miami CountyBattery storage Β· 100 MW Β· withdrawn
- Battery storage project AH1-322, Miami CountyBattery storage Β· 90.0 MW Β· withdrawn
- Battery storage project AH1-321, Miami CountyBattery storage Β· 54.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem