United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in PJM (Mid-Atlantic, Midwest) (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown505,495 MW
Active in queue16.6 GW178 requests
Agreement signed11.1 GW128 requests
Withdrawn71947.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

50 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Dolphin Solar
Solar · Dolphin Solar LLC
450 MWIn study Fountain, INPJM Sep 2020target 2024
Pleasant Grove Solar
Solar · Deriva Energy Solar, LLC
300 MWIn study Mchenry, ILPJM Mar 2020target 2023
Butterfly Meadows
Solar · Butterfly Meadows Solar Project, LLC
300 MWIn study Van Wert, OHPJM Sep 2020target 2024
Dawson Solar
Solar · Deriva Energy Solar, LLC
300 MWIn study Mclean, ILPJM Sep 2020target 2024
Burr Oak Solar
Solar · Leeward Renewable Energy Development, LLC
300 MWIn study Dekalb, ILPJM Aug 2020target 2023
South Dixon Solar
Solar · Deriva Energy Solar, LLC
300 MWIn study Lee, ILPJM Mar 2020target 2022
Beacon Solar
Solar · Beacon Solar, LLC
260 MWIn study Rock Island, ILPJM Sep 2020target 2023
Gipper Solar Farm
Solar · Gipper Solar Farm, LLC
255 MWIn study Whiteside, ILPJM Oct 2020target 2023
Steward Creek Solar
Solar · Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Mar 2020target 2023
Teays River Wind Farm
Onshore wind · Teays River Wind Farm LLC f/k/a Blackford County Wind Farm LLC
200 MWIn study Blackford, INPJM Mar 2020target 2023
Cass County Solar
Solar + storage · Steelhead Solar, LLC
200 MWIn study Cass, MIPJM Mar 2020target 2023
Riverbank Energy
Battery storage · Lincoln Reserve Energy, LLC
200 MWIn study Cook, ILPJM Mar 2020target 2024
Courthouse Solar
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
167 MWIn study Charlotte, VAPJM Mar 2020target 2031
Bright Stalk Generating Facility
Solar · Lexington Chenoa Wind Farm LLC
150 MWIn study Mclean, ILPJM Mar 2020target 2022
Osagrove Flats Solar
Solar · Aurora Solar LLC
150 MWIn study Lasalle, ILPJM Mar 2020target 2023
Otter Creek Solar
Solar · Aurora Solar LLC
150 MWIn study Lasalle, ILPJM Mar 2020target 2023
Rosegold Solar
Solar · Leeward Renewable Energy Development, LLC
150 MWIn study Blackford, INPJM Jan 2020target 2022
Kankakee Solar
Solar · AEUG Kankakee Solar, LLC
144 MWIn study Kankakee, ILPJM Feb 2020target 2021
Bluestem Solar
Solar · RWE Solar Development, LLC
125 MWIn study Laporte, INPJM Sep 2020target 2023
Butterfly Meadows
Battery storage · Butterfly Meadows Solar Project, LLC
100 MWIn study Van Wert, OHPJM Sep 2020target 2024
Steward Creek Solar
Solar · Steward Creek Solar, LLC
100 MWIn study Lee, ILPJM Mar 2020target 2023
Grand Marsh Solar
Solar · Deriva Energy Solar, LLC
100 MWIn study Kankakee, ILPJM Mar 2020target 2023
Red Maple Solar
Solar · Red Maple Solar, LLC
95.1 MWIn study Dekalb, ILPJM Aug 2020target 2023
Wild Rose Solar Project
Solar · Wild Rose Solar Project, LLC
90.0 MWIn study Nelson, VAPJM Aug 2020target 2024
Brunswick Battery Storage
Battery storage · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
75.0 MWIn study Brunswick, VAPJM Sep 2020target 2031
Cerulean Solar and Mulberry BESS
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
62.0 MWIn study Richmond, VAPJM Feb 2020target 2031
Moon Corner Solar
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
60.0 MWIn study Richmond, VAPJM Sep 2020target 2031
Bluestem Solar
Battery storage · RWE Solar Development, LLC
55.0 MWIn study Laporte, INPJM Sep 2020target 2023
Top Crop Generating Facility
Battery storage · Blackstone Wind Farm, LLC
50.0 MWIn study Lasalle, ILPJM Mar 2020target 2023
Top Crop Generating Facility
Battery storage · Blackstone Wind Farm, LLC
50.0 MWIn study Lasalle, ILPJM Mar 2020target 2023
Paulding Storage II
Battery storage · Paulding Wind Farm II LLC
50.0 MWIn study Paulding, OHPJM Mar 2020target 2023
South Branch Solar
Solar
46.0 MWPaused / redesign Hancock, OHPJM Jul 2020target 2025
Redbud-Gaylord 34.5 kV
Solar
30.0 MWPaused / redesign Frederick, VAPJM Jul 2020target 2026
Black Diamond Solar
Battery storage · Black Diamond Solar Power, LLC
30.0 MWIn study Christian, ILPJM Sep 2020target 2022
Amelia Energy Facility
Solar · Amelia Energy Facility, LLC
25.0 MWIn study Amelia, VAPJM Feb 2020target 2022
Amelia Energy Facility
Solar · Amelia Energy Facility, LLC
20.0 MWIn study Amelia, VAPJM May 2020target 2023
Switchgrass Solar 1
Solar
20.0 MWPaused / redesign Accomack, VAPJM Feb 2020target 2025
Norwegian Solar
Solar
19.8 MWPaused / redesign Northumberland, PAPJM Apr 2020target 2024
Jarratt Energy Facility 2
Solar · Jarratt Energy Facility, LLC
18.0 MWIn study Greensville, VAPJM Mar 2020target 2022
Solar project AF2-294, Wayne County
Solar
17.0 MWPaused / redesign Wayne, PAPJM Mar 2020target 2025
Stony Creek Solar
Solar
15.0 MWPaused / redesign Somerset, PAPJM Mar 2020target 2025
Morgan Street-Cochranton 34.5 kV
Solar
15.0 MWPaused / redesign Crawford, PAPJM Sep 2020target 2026
Aurora Battery Storage
Battery storage
10.0 MWPaused / redesign Will, ILPJM Oct 2020target 2028
NJ Land Phase II
Solar
10.0 MWPaused / redesign Burlington, NJPJM Mar 2020target 2025
Scout Storage I
Battery storage
9.0 MWPaused / redesign Accomack, VAPJM Jan 2020target 2026
Barbertown Solar
Solar
7.0 MWPaused / redesign Hunterdon, NJPJM Mar 2020target 2026
Furnace View Farms
Solar
5.0 MWPaused / redesign Berks, PAPJM Sep 2020target 2023
Greenfield CSG 1
Solar
4.0 MWPaused / redesign Erie, PAPJM Sep 2020target 2025
Springfield CSG 1
Solar
3.9 MWPaused / redesign Delaware, PAPJM Sep 2020target 2024
Great Lake Growers
Solar
2.6 MWPaused / redesign Erie, PAPJM Sep 2020target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)