United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
SOLAR Β· PJMGreenfield CSG 1
Greenfield CSG 1 is a 4.0 MW solar request suspended in the PJM interconnection queue, in Erie County, Pennsylvania, connecting to PENELEC.
- PlanningQueued Sep 2020 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AG1-253
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PENELEC
- Connection point (POI)
- Erie East-Union City 34.5 kV
- Location
- Erie County, Pennsylvania
- Technology
- Solar: 4.0 MW
- Total requested
- 4.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Suspended
- Entered queue
- 25 September 2020
- Proposed online date
- May 2025
Location
Marker shows the centre of Erie County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Erie County
- French Creek Solar and BESSSolar + storage Β· 150 MW Β· agreement signed
- Wilson SolarSolar Β· 80.0 MW Β· agreement signed
- Union City 34.5 kVSolar Β· 12.0 MW Β· agreement signed
- Battery storage project AI1-188, Erie CountyBattery storage Β· 130 MW Β· in study
- Solar project AI1-030, Erie CountySolar Β· 5.0 MW Β· in study
- Solar project AH2-014, Erie CountySolar Β· 5.0 MW Β· in study
- Erie East EnergyBattery storage Β· 160 MW Β· suspended
- Great Lake GrowersSolar Β· 2.6 MW Β· suspended
- Erie SolarSolar Β· 20.0 MW Β· built
- Gas project B50, Erie CountyGas Β· 500 MW Β· withdrawn
- Gas project M15, Erie CountyGas Β· 302 MW Β· withdrawn
- Gas project H22, Erie CountyGas Β· 300 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem