United States › Grid › Interconnection queues › Pennsylvania

SOLAR · PJM

Union City 34.5 kV

Union City 34.5 kV is a 12.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Erie County, Pennsylvania, connecting to PENELEC.

Queue statusConsented
  1. PlanningQueued Sep 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AG1-198
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Union City 34.5 kV
Location
Erie County, Pennsylvania
Technology
Solar: 12.0 MW
Total requested
12.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Active
Entered queue
18 September 2020
Proposed online date
December 2025

Location

Marker shows the centre of Erie County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Erie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem