BATTERY STORAGE · PJM

Scout Storage I

Scout Storage I is a 9.0 MW battery storage request suspended in the PJM interconnection queue, in Accomack County, Virginia, connecting to DPL.

Queue statusPaused / redesign
  1. PlanningQueued Jan 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AF2-060
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DPL
Connection point (POI)
Wattsville 12 kV
Location
Accomack County, Virginia
Technology
Battery: 9.0 MW
Total requested
9.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Suspended
Entered queue
25 January 2020
Proposed online date
April 2026

Location

Marker shows the centre of Accomack County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Accomack County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem