United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in ISO-NE (New England) (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1139,841 MW
Active in queue129 MW4 requests
Agreement signed129 MW4 requests
Withdrawn1139,841 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

113 requests Β· page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore Wind Increase
Offshore wind
1,200 MWWithdrawn / abandoned CTISO-NE Sep 2020target 2027
Offshore Wind
Offshore wind
1,200 MWWithdrawn / abandoned CTISO-NE Sep 2020target 2027
Offshore Wind
Offshore wind
1,200 MWWithdrawn / abandoned MAISO-NE Sep 2020target 2027
Combined Cycle
Gas
800 MWWithdrawn / abandoned Suffolk, MAISO-NE Apr 2020target 2024
Combined Cycle
Gas
800 MWWithdrawn / abandoned Suffolk, MAISO-NE Apr 2020target 2024
Battery Storage
Battery storage
700 MWWithdrawn / abandoned Suffolk, MAISO-NE Aug 2020target 2024
Battery Storage
Battery storage
500 MWWithdrawn / abandoned Middlesex, MAISO-NE Aug 2020target 2025
Battery Storage
Battery storage
204 MWWithdrawn / abandoned Middlesex, MAISO-NE Oct 2020target 2025
Battery Storage
Battery storage
200 MWWithdrawn / abandoned Androscoggin, MEISO-NE Jan 2020target 2022
Battery Storage
Battery storage
200 MWWithdrawn / abandoned New Haven, CTISO-NE Apr 2020target 2026
Battery Storage
Battery storage
200 MWWithdrawn / abandoned Middlesex, MAISO-NE Oct 2020target 2023
Storage
Battery storage
150 MWWithdrawn / abandoned Middlesex, MAISO-NE Apr 2020target 2023
Solar
Solar
135 MWWithdrawn / abandoned Hartford, CTISO-NE Sep 2020target 2022
Solar
Solar
120 MWWithdrawn / abandoned Penobscot, MEISO-NE May 2020target 2023
Battery Storage
Battery storage
112 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2020target 2024
Battery Storage
Battery storage
112 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2020target 2024
Battery Storage
Battery storage
102 MWWithdrawn / abandoned Kennebec, MEISO-NE Nov 2020target 2023
Solar
Solar
100 MWWithdrawn / abandoned Penobscot, MEISO-NE Nov 2020target 2024
Solar
Solar
100 MWWithdrawn / abandoned Penobscot, MEISO-NE Sep 2020target 2024
Solar
Solar
100 MWWithdrawn / abandoned Penobscot, MEISO-NE Oct 2020target 2024
Battery Storage
Battery storage
100 MWWithdrawn / abandoned Fairfield, CTISO-NE Sep 2020target 2023
Solar
Solar
90.0 MWWithdrawn / abandoned Oxford, MEISO-NE May 2020target 2021
Solar plus battery storage
Solar + storage
85.0 MWWithdrawn / abandoned Carroll, NHISO-NE Jul 2020target 2023
Solar
Solar
76.3 MWWithdrawn / abandoned Merrimack, NHISO-NE Aug 2020target 2025
Solar
Solar
65.0 MWWithdrawn / abandoned Oxford, MEISO-NE Oct 2020target 2024
Solar
Solar
60.0 MWWithdrawn / abandoned Coos, NHISO-NE Jun 2020target 2023
Solar
Solar
60.0 MWWithdrawn / abandoned Coos, NHISO-NE Jun 2020target 2023
Eversource Group Study @ Wareham
Solar + storage
55.1 MWWithdrawn / abandoned Plymouth, MAISO-NE Mar 2020target 2023
Solar
Solar
51.0 MWWithdrawn / abandoned Grafton, NHISO-NE Jan 2020target 2022
Battery Storage
Battery storage
50.0 MWWithdrawn / abandoned New Haven, CTISO-NE Aug 2020target 2022
Kent County - NG WRI DG Area Study #2 >5 MW
Solar
49.8 MWWithdrawn / abandoned Kent, RIISO-NE Aug 2020target 2025
Eversource Group @ Wareham 714
Solar + storage
48.0 MWWithdrawn / abandoned Plymouth, MAISO-NE Apr 2020target 2023
Eversource Group @ West Pond 737
Solar + storage
44.1 MWWithdrawn / abandoned Plymouth, MAISO-NE Apr 2020target 2023
Solar
Solar
40.0 MWWithdrawn / abandoned Androscoggin, MEISO-NE Mar 2020target 2022
Solar
Solar
40.0 MWWithdrawn / abandoned Hampshire, MAISO-NE Jun 2020target 2023
Wood River - NG WRI DG Area Study #2 >5 MW
Solar
34.4 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2020target 2025
Eversource Group @ Tremont Substation 713
Solar + storage
33.7 MWWithdrawn / abandoned Plymouth, MAISO-NE Apr 2020target 2023
Eversource Group @ Industrial Park 636
Solar + storage
29.1 MWWithdrawn / abandoned Bristol, MAISO-NE Apr 2020target 2023
Eversource Group @ Fisher Rd Substation 657
Solar + storage
27.9 MWWithdrawn / abandoned Bristol, MAISO-NE Apr 2020target 2023
Solar
Solar
27.0 MWWithdrawn / abandoned Grafton, NHISO-NE Dec 2020target 2022
Eversource Group @ Rochester #745
Solar + storage
24.6 MWWithdrawn / abandoned Plymouth, MAISO-NE Apr 2020target 2023
Eversource Group Study @ Crystal Spring
Solar + storage
20.5 MWWithdrawn / abandoned Plymouth, MAISO-NE Mar 2020target 2023
Solar
Solar
20.0 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2020target 2028
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2020target 2024
Eversource Group @ Wing Lane 624
Solar + storage
19.0 MWWithdrawn / abandoned Bristol, MAISO-NE Apr 2020target 2023
Solar
Solar
17.2 MWWithdrawn / abandoned Sagadahoc, MEISO-NE Apr 2020target 2030
Solar
Solar
17.0 MWWithdrawn / abandoned Oxford, MEISO-NE Jan 2020target 2024
Solar
Solar
16.0 MWWithdrawn / abandoned Hillsborough, NHISO-NE Apr 2020target 2024
Kent County - NG WRI DG Area Study #2 <5 MW
Solar
13.5 MWWithdrawn / abandoned Kent, RIISO-NE Aug 2020target 2022
Eversource Group Study @ Blandford
Solar
12.5 MWWithdrawn / abandoned Hampden, MAISO-NE Apr 2020target 2023
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)