Battery Storage

Battery Storage is a 100 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Fairfield County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2020 (completed)
  2. Withdrawn / abandonedDec 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1062
Grid region
ISO-NE (New England)
Connection point (POI)
Baird substation
Location
Fairfield County, Connecticut
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
10 September 2020
Proposed online date
June 2023
Withdrawn
December 2020

Location

No county location in the queue data.