United States β€Ί Grid β€Ί Interconnection queues β€Ί New Hampshire

SOLAR Β· ISO-NE

Solar

Solar is a 16.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Hillsborough County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedMay 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1016
Grid region
ISO-NE (New England)
Connection point (POI)
At the Eversource NH 314 line (34.5kV) out of the South Milford substation.
Location
Hillsborough County, New Hampshire
Technology
Solar: 16.0 MW
Total requested
16.0 MW
Service type
Energy only (ERIS)
Study phase
In Progress
Queue status
Withdrawn
Entered queue
24 April 2020
Proposed online date
November 2024
Withdrawn
May 2024

Location

Marker shows the centre of Hillsborough County; the queue data does not give exact sites.

Power plants in New Hampshire Β· Transmission lines in New Hampshire

Other requests in Hillsborough County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem