United States βΊ Grid βΊ Interconnection queues βΊ New Hampshire
SOLAR Β· ISO-NESolar
Solar is a 20.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Hillsborough County, New Hampshire.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2017 (completed)
- Withdrawn / abandonedJan 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 679
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Eversource NH 34.5 kV line 313, between South Peterborough and Monadnock substations. The Project will tap this line at about 0.1-0.5 miles south of the South Peterborough substation.
- Location
- Hillsborough County, New Hampshire
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress
- Queue status
- Withdrawn
- Entered queue
- 3 August 2017
- Proposed online date
- July 2022
- Withdrawn
- January 2021
Location
Marker shows the centre of Hillsborough County; the queue data does not give exact sites.
Power plants in New Hampshire Β· Transmission lines in New Hampshire
Other requests in Hillsborough County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem